i. 600 MW Solar Power Park in Jhansi

  • Foundation stone laid by Prime Minister on 19.11.21.
  • Total 2700 Acres land  has been acquired for the project.
  • DPR amounting to Rs. 331.71 Cr. has been approved by THDCIL board on 19.05.2025.
  • Work of Internal and External Power Evacuation System is in progress.
  • Selection of Solar Power Developer (SPD) is in process.
  • Development of Solar Power Park shall be done by Mar’26.

ii. 600 MW Solar Power Park in Lalitpur

  • Foundation stone laid by Prime Minister on 04.03.2024.
  • Out of 2700 Acres required land, 2380 acres (approx. 88.15 %) has been acquired for the project.
  • DPR amounting to Rs. 347.78 Cr. has been approved by THDCIL Board on 19.05.2025.
  • Work of Internal and External Power Evacuation System is in progress.
  • The Implementation Support Agreement (ISA) for execution of Project as SPD has been signed with NTPC-REL on 24.10.2025.
  • Development of Solar Power Park shall be done by Mar’26.

iii. 800 MW Solar Power Park in Chitrakoot

  • Foundation stone laid by Prime Minister on 18.12.2023.
  • Out of reassessed 3600 required land, 3292.03 acres (approx. 91.45%) has been acquired for the project.
  • DPR amounting to Rs. 485.26 Cr. has been approved by THDCIL Board on 19.05.2025.
  • Work of Internal and External Power Evacuation System is in progress.
  • The Implementation Support Agreement (ISA) for execution of Project as SPD has been signed with NTPC-REL on 24.10.2025.
  • Development of Solar Power Park shall be done by Mar’26.

Floating Solar Power Projects

After PFR, DPRs of following three projects have been prepared and are under review:

  • Mata Tila Dam & Reservoir, Lalitpur (400 MW)
  • Jamini Dam & Reservoir, Lalitpur (37 MW)
  • Arjun Sagar, Mahoba (27 MW)

Proposal for issuing NOC for implementation of above projects by THDC/TUSCO has been submitted in the Cabinet of GoUP. Matter is under process with GoUP.