Type Title Author Comments Last updated
Photo Gallery Khurja-Limestone Crusher House: Structural and equipment erection in progress thdc-admin 0 3 weeks ago
Photo Gallery Khurja-View of Cooling Tower 1 & 2 thdc-admin 0 3 weeks ago
Photo Gallery Khurja-Railway Siding: ROR Portal Beam-2 fabrication nearing completion. thdc-admin 0 3 weeks ago
Photo Gallery Khurja-Railway Siding: Sacrificial shuttering for P4-P5 span of ROR thdc-admin 0 3 weeks ago
Photo Gallery Khurja-Unit-1 Boiler Steam Blowing started on 18.05.24 thdc-admin 0 3 weeks ago
Photo Gallery Khurja-Unit1 Main Boiler Light Up successfully conducted on 21.03.24. thdc-admin 0 3 weeks ago
Photo Gallery Khurja-TG Floor Unit-1 thdc-admin 0 3 weeks ago
Photo Gallery Khurja-Transformer Yard thdc-admin 0 3 weeks ago
Photo Gallery Khurja-Railway Siding-Locomotive rolling testing done from downline thdc-admin 0 3 weeks ago
Photo Gallery Khurja-ROR-PSC slab placed in position for Bridge-27 thdc-admin 0 3 weeks ago
Photo Gallery Khurja-CHP- Coal Crusher House thdc-admin 0 3 weeks ago
Photo Gallery Khurja-CHP: WT-1 Apron Feeder and Dribble conveyor trail load successfully completed thdc-admin 0 3 weeks ago
Photo Gallery Khurja-CHP-Hydraulic arm testing thdc-admin 0 3 weeks ago
Photo Gallery Khurja-CHP-Hydro test of Stacker Reclaimer-1 completed thdc-admin 0 3 weeks ago
Photo Gallery Khurja-CWPH is Operational thdc-admin 0 3 weeks ago
Photo Gallery Khurja-RWPH_is_in_service thdc-admin 0 3 weeks ago
Photo Gallery PSP-Erection work of MIV-3 is in progress thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-BFV-03 Erection work is in progress thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-Pre-assembly of MIV-4 is in progress at service bay thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-Erection work of BFV-4 in progress thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-USSS-02 Lining thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-MIV-3 Erection thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-BFV-3 Erection thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-Unit-1 Mechanical Spinning completed thdc-admin 0 3 weeks 1 day ago
Photo Gallery PSP-All TRT outlet works including river joining works have been completed thdc-admin 0 3 weeks 1 day ago