Photo Gallery |
Khurja-Bird Eye View of Khurja STPP |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Generator Unit-1 ATT completed |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-ESP-1 Pass-A, B&C Field charging completed |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-1st Coal Rake reached Khurja STPP site, 07.08.24 |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Coal wagon unloading at Wagon Tippler-1 |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Unit-1 Boiler Coal Feeding System- Bunker and Tripper work in progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Railway Siding works- ROR Bridge - Portal Beams and Composite Girders Launched successfully. |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-TAC work in advance stage of progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Ash Handling Pipeline work in progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Unit-1 Steam Blowing completed on 30.06.24. |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-UNIT-2 TG Boxed up on 25.06.24 |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Unit-1 GTs Fire-fighting demonstration successfully completed |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-SG Pkg - Tripper erection & Conveyor erection in progress from TP-8 to Boiler-1 |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Chimney-2 Flue can erection in progress. |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Railway Siding - 1st ROR Portal beam launched on 10.07.24. |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-CHP- Work of Bulk Receiving Unit in progress. |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-WTP - Clarifier-2 Trial test completed & Water filling in progress. |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-General view of Khurja STPP |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Unit-1: Steam blowing in progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Turbine Unit-2 erection in progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Unit-2: CW Duct work in progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-ESP-1 works in progress |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Chimney-2 and FGD Absorber-2 |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Wagon Tippler-1: Empty Wagon tippling test successfully conducted |
thdc-admin |
3 weeks ago |
Photo Gallery |
Khurja-Wagon Tippler-2: Equipment erection under progress |
thdc-admin |
3 weeks ago |