| Allotment Agreement |
The Allotment Agreement between Ministry of Coal & THDC India Ltd has been signed on 15.12.2016. |
| Allotment Order |
Allotment Order of Amelia Coal Mine has also been issued to THDCIL on 17.01.2017. |
| Investment Approval |
CCEA accorded investment approval at an estimated cost of Rs. 1587.16 Cr. (Dec-17 PL) on 07.03.2019. |
| Forest Clearance |
Stage-II Forest Clearances for 843 Ha. forest land accorded by MoEF&CC, GoI on 15.02.2021. |
| Mining Plan |
Revised Mining Plan has been approved on 13.03.2020 by MoC. |
| Land |
Entire 1412.37 Ha Land of Amelia Coal Mine has been handed over to THDCIL. |
| Environmental Clearance |
MoEF&CC accorded approval for grant of transfer of Environmental Clearance (EC) to THDCIL on 03.08.2021. |
| Mining Lease |
Mining Lease was sanctioned by Mineral Resource Department, GoMP on 16.08.2021. Mining lease deed signed between THDCIL & District Collector, Singrauli on 24.08.2021. |
| Mine opening permission |
Granted by CCO, Kolkata (MoC) on 15.02.22. |
| Appointment of MDO |
Mine is being operated in MDO mode by M/s Amelia Coal Mining Ltd. |
| Power Supply Connection |
Agreement for Connection of 8 MVA HT Line has been executed between THDCIL and MPPKVVCL on 02.05.2020. |
| Land for CEC & Railway Siding |
Approx. 26.70 Ha Govt., Forest & Private Land has been acquired for Coal Evacuation Corridor of 25 m width & Railway Siding. |
| Opening of Mine |
Mine has been opened on 17.11.2022 |
| Coal Production |
Coal extraction has been started from 18.02.23. |
| Commercial Operation |
Commercial Operation Date (COD) of Amelia Coal Mine has been successfully achieved on 18.02.2025. |