Khurja Super Thermal Power Project

S. No. Title Event Date
41 Locomotive rolling from Danwar station to THDC yard conducted successfully
42 Boiler Light Up at KSTPP, Khurja: A Milestone Achievement
43 Boiler Light Up at KSTPP, Khurja: A Milestone Achievement
44 Shri Pankaj Agarwal, Secretary (Power), MoP, Shri Praveen Gupta, Member (Thermal), CEA and Shri Piyush Singh, Joint Secretary (Thermal)on official visit to review the progress of the 1320 MW Khurja Super Thermal Power Project (STPP)
45 Commissioning of Main DM Water Production Plant and Cooling Water Pump at KSTPP, Khurja
46 Significant project milestones achieved at KSTPP, Khurja
47 Raw Water Pumps become operational at KSTPP, Khurja
48 THDC India Limited, Premier Power Sector PSU gears up for the issuance of Corporate Bond Series-IX
49 THDC India Limited, Premier Power Sector PSU gears up for the issuance of Corporate Bond Series-IX
50 Director (Technical) Visited KSTPP
51 Turbine Box Up: Khurja STPP(2X660MW)
52 Charging of Station Transformer # 1: Khurja STPP(2X660MW)
53 Commencement of Turbine Generator Erection Unit#1 at Khurja STPP
54 Khurja STPP: Construction attained a juncture with commencement of Ceiling Girder of Unit
55 TG Deck Casting: One more milestone caved of Khurja S.T.P.P.