| Date | Event |
| 06.12.2013 | Completion of land acquisition critical to project |
| 01.01.2009 | Submission of Forest Proposal |
| 03.06.2011 | Receipt of Stage-I Forest clearance |
| 05.04.2014 | Receipt of Working permission |
| 28.05.2013 | Receipt of Stage-II Forest clearance |
| 20.12.2012 | Receipt of Wild-life Clearance |
| 22.08.2007 | Receipt of Environment Clearance |
| 10.04.2007 | Receipt of Clearances from State Pollution Control Board |
| 26.02.2007 | PIB/EFC proposal Approval |
| 21.08.2008 | CCEA Approval/Investment approval |
| 19.12.2013 | Award of EPC Contract to M/s HCC Ltd. for Civil Works & HM Equipment works including penstock steel liners |
| 17.10.2014 | Award of EPC Contract to M/s BHEL for EM Works |
| 02.04.2018 | River Diversion |
| 16.11.2023 | Completion of TBM Entry Adit through TBM |
| 17.11.2023 | Start of HRT construction through TBM |
| 03.08.2024 | Erection of EoT in Service Bay completed. |
| 01.11.2024 | TRT Lining started. |
| 20.11.2024 | Erection of DT liner in Unit -1 completed. |
| 16.01.2025 | Erection of DT liner completed in Unit -2. |
| 22.02.2025 | EoT crane extension up to Unit-1 |
| 30.04.2025 | Machine Hall excavation |
| 21.06.2025 | Widening of U/S Surge Shaft |
| 05.07.2025 | EoT crane extension up to Unit-2 |
| 31.08.2025 | Assembly of Rotor of Unit-1 |
| 22.09.2025 | Erection of spiral casing and completion of Hydro Static test of Unit-1 |
| 22.11.2025 | In Transformer Hall, EOT Crane in Unit -1 of GIS Hall commissioned |
| 02.12.2025 | In Machine Hall, after erection & successful completion of Hydrostatic Test (HST) of the spiral casing of Unit-2 on 02.12.2025 |