EM Works:
Unit-1 & 2: COD of Unit 1 & 2 declared on 07.06.2025 & 10.07.2025 respectively.
Unit-3: Unit has been successfully synchronized in Pump Condenser mode on 25.11.2025, followed by the first successful pumping of water from the lower to the upper reservoir on 28.11.2025. Trial run of the unit was performed successfully on 10.12.2025 and COD of Unit-3 declared w.e.f. 00:00 hrs. from 12.12.2025.
Unit-4: Dry commissioning tests almost completed. VSI cold commissioning will be taken up in due course of time. COD of the Unit is targeted by Mar-26.
Civil & Hydro-Mechanical Works:
Butterfly Valves for Unit-3 & 4: BFV-3 & 4 have been commissioned
Main Inlet Valves for Unit- 3 & 4: MIV-3 have been commissioned.