- Proposal for allotment of 10000 Acres (4000 Ha) Govt. Land for development of 2000 MW Solar Park under Phase-I is in process of State Cabinet approval.
- MNRE has conveyed In-principle approval on 01.02.24 for development of Bodana Solar Park in District Jaisalmer, Rajasthan with 1292 MW capacity by TREDCO under mode 8 of Solar Park Scheme, being developed in Phase-I.
- DPR Preparation for 1292 MW Bodana Solar Power Park is in advanced stage.
- MNRE has issued authorization certificate to apply for connectivity in Inter-state Transmission System for Bodana Solar Park by TREDCO.
- Proposal for waiver of Security Charges at the tune of Rs. 20 Crores against allocation of 10,000-acre Govt. Land is in process.
- Loan assistance of Rs. 355.86 Crores for 2000 MW sanctioned by REC Ltd. on 11.01.2024.
Last Updated on 24/8/2024