i. 600 MW Solar Power Park in Jhansi

  • Foundation stone laid by Prime Minister on 19.11.21.
  • Out of 2700 Acres required land approx. 96 % land has been acquired for the project.
  • DPR for Rs. 429.92 Cr approved by MNRE on 20.06.2022.
  • CFA of Rs 34.56 Cr has been received from MNRE.
  • In-principle consent for signing PPA of capacity 600 MW has been received from UPPCL.
  • Work of Internal and External Power Evacuation System is in progress.
  • Project targeted to be commissioned by Dec-25.

ii. 600 MW Solar Power Park in Lalitpur

  • Foundation stone laid by Prime Minister on 04.03.2024.
  • Out of 2700 Acres required land approx. 86 % land has been acquired for the project.
  • DPR for Rs. 449.23 Cr. under approval by MNRE.
  • MNRE disbursed the first instalment of CFA Rs 24 Cr on 10.01.2024.
  • Work of External Power Evacuation System is in progress.
  • Project is targeted to be commissioned by Jun-26.

iii. 800 MW Solar Power Park in Chitrakoot

  • Foundation stone laid by Prime Minister on 18.12.2023.
  • Out of 3400 Acres required land approx. 90 % land has been acquired for the project.
  • DPR is under process of approval from MNRE.
  • CFA of Rs 25 Lakhs has been received on 06.09.2023 from MNRE against Milestone “Preparation of DPR”.
  • 49.42 acres land for construction of External Power Evacuation System & Grid Connectivity handed over to UPPTCL.
  • Project is targeted to be commissioned by Jun-26.

Floating Solar Power Projects

After PFR, DPRs of following three projects have been prepared and are under review:

  • Mata Tila Dam & Reservoir, Lalitpur (400 MW)
  • Jamini Dam & Reservoir, Lalitpur (37 MW)
  • Arjun Sagar, Mahoba (27 MW)

Proposal for issuing NOC for implementation of above projects by THDC/TUSCO has been submitted in the Cabinet of GoUP. Matter is under process with GoUP.