1. All necessary clearances FC, EC, Mining Lease and CTE accorded.
  2. Entire 1412.37 Ha land including Govt. & Pvt. land required for Amelia Coal Mine has been handed over to THCIL. However, for physical possession of private land, shifting of PAFs is under progress.
  3. Mine is being operated in MDO mode by M/s Amelia Coal Mining Ltd.
  4. Mine has been operated on 17.11.2022.
  5. Coal Extraction has been started from 18.02.23.
  6. Coal Dispatch from Railway Siding at Deoragram Railway Station to NTPC started from 29.06.23 and till date 3.2 Lakh Ton Coal has been dispatched so far.
  7. Till date 5.3 Million Cubic Meter Over Burden has been removed and 0.49 million Ton Coal production has been done.