Introduction
The Project having an installed capacity of 63 MW, comprises of 30 nos. Wind Turbine Generators (WTGs), each of 2.1 MW capacity These 30 WTGs are installed in seven villages namely Jampar, Kotadiya, Fot, Kandorna, Gundala, Gunda & Bajana situated in Bhanvad and Kandorna Windfarms in Distt. Devbhumi Dwarka, Gujarat which is approx. 190 Kms. from Rajkot and 410 Kms. from Ahmedabad.
COMMISSIONING OF PROJECT:The Project has been commissioned on 31.03.2017. The expected Annual Energy Production (AEP) from the Project is 144.9 MU with 26.27% CUF. The Power Purchase Agreement (PPA) for the project has been signed with Gujarat Urja Vikas Nigam Limited (GUVNL) at a fixed tariff of Rs. 4.19 / unit for 25 years.
The project has been registered with IREDA for availing Generation Based Incentive (GBI) @ Rs. 0.50 / kWh with a cap of 1 Crore per MW. The project is entitled to receive a total GBI of 63 Crores under this scheme of Ministry of New & Renewable Energy.
The project has generated total energy of 1121.06 MU as on 30th June 2024 since commissioning of the project.