i. 600 MW Solar Power Park in Jhansi

  • Foundation stone laid by Prime Minister on 19.11.21.
  • Out of 2700 Acres required land approx. 98 % land has been acquired for the project.
  • Revised cost of DPR amounting of Rs.409.93 Cr. has been approved by TUSCO Board on 14.08.2024 and sent to THDCIL board for appraisal and investment approval.
  • Total CFA of Rs.72 Crore has been released by MNRE.
  • In-principle consent for signing PPA of capacity 600 MW has been received from UPPCL with tariff ceiling of Rs. 2.70/unit, with the provision of tariff ceiling.
  • Work of Internal and External Power Evacuation System is in progress.
  • Loan agreement (Rs.140.47 Cr.) with M/s REC Ltd. has been signed on 19.05.2023 for development of 600 MW Ultra Mega Jhansi Solar Park.
  • Development of Solar Power Park shall be done by Dec’25.

ii. 600 MW Solar Power Park in Lalitpur

  • Foundation stone laid by Prime Minister on 04.03.2024.
  • Out of 2700 Acres required land approx. 87.2 % land has been acquired for the project.
  • Revised DPR amounting of Rs.422.12 Cr. has been approved by TUSCO Board on 14.08.2024 and sent to THDCIL board for appraisal and investment approval.
  • MNRE disbursed the first instalment of CFA Rs 24 Cr on 10.01.2024.
  • Internal Power Evacuation System: LOA for PMC services issued to M/s GERMI on 18.09.2024.
  • Work of External Power Evacuation System is in progress.
  • TUSCO Board has accorded approval for implementation of 600 MW Lalitpur Solar Power Project by THDCIL under EPC mode as Solar Project Developer (SPD), in line with MNRE guidelines.
  • Development of Solar Power Park shall be done by Dec’25.

iii. 800 MW Solar Power Park in Chitrakoot

  • Foundation stone laid by Prime Minister on 18.12.2023.
  • Out of reassessed 3600 required land approx. 89.32% land has been acquired for the project.
  • Revised DPR amounting to Rs.485.26 Cr. has been submitted to MNRE/SECI for approval on 06.09.2024 after approval from TUSCO Board.
  • CFA of Rs.25 Lakhs has been received on 06.09.2023 from MNRE against Milestone “Preparation of DPR”.
  • Internal Power Evacuation System: LOA for PMC services issued to M/s GERMI on 18.09.2024.
  • 49.42-acre land for construction of External Power Evacuation System & Grid Connectivity handed over to UPPTCL.
  • TUSCO Board has accorded approval for implementation of 800 MW Chitrakoot Solar Power Project by THDCIL under EPC mode as Solar Project Developer (SPD), in line with MNRE guidelines.
  • Development of Solar Power Park shall be done by Dec’25.

Floating Solar Power Projects

After PFR, DPRs of following three projects have been prepared and are under review:

  • Mata Tila Dam & Reservoir, Lalitpur (400 MW)
  • Jamini Dam & Reservoir, Lalitpur (37 MW)
  • Arjun Sagar, Mahoba (27 MW)

Proposal for issuing NOC for implementation of above projects by THDC/TUSCO has been submitted in the Cabinet of GoUP. Matter is under process with GoUP.