• Boiler Hydro Test of Unit-1 & 2 successfully completed on 15.03.23 & 02.11.23 respectively.
  • Boiler-1 light up done on 21.03.24. Unit-1 Steam blowing also completedsuccessfully on 30.06.24.
  • Chimney-1 is operational. In Chimney-2, flue-can erection nearing completion. Field charging in all six passes in ESP-1 has been completed; Hopper heaters installed, charging, insulation and cladding work nearing completion.
  • Unit-1 IPBD and GTs are ready for charging. TG-1 HP Bypass system, LP Bypass system and Main Turbine governing system commissioned.
  • In Ash Dyke Lagoon-2 is ready for charging; Lagoon-1 & OFL Lagoon readiness for charging in advance stage.
  • 400 kV Switchyard, Transmission Lines & Sub-station are ready for power evacuation.
  • CT-1 is ready. In CT-2 all fans, motors, gearbox installed. Cable laying also completed. Panel installed and testing in progress.
  • Wagon Tippler-1 and Coal Crusher is operational. Coal path-1 including SR-1 is also ready and stacking of coal in stockyard commenced. WT-2 civil works completed; structural/ equipment erection in progress. Work in Limestone Handling plant also in progress.
  • Initial 10 no. of Coal rake from captive Amelia Coal Mine (Singrauli, MP) received at Khurja STPP and successfully unloaded and stacked at Khurja stockyard.
  • Railway siding works are in advance stage of completion. Downline from Danwar station of Indian Railways to Khurja STPP is operational.
  • In Unit-2, all GTs, UTs placed at foundation and associated erection works/ testing taken up. Further, main boiler, ESP, FGD and other associated works are in progress.
  • Facility for water supply from Ganga canal at Mundakhera to Khurja STPP is operational long back and water is being supplied to the Khurja plant.