•    Boiler Hydro Test of Unit-1 & 2 successfully completed on 15.03.23 and 02.11.23 respectively.

•    Boiler-1 light up done on 21.03.24. Unit-1 Steam blowing completed successfully on 30.06.24.

•    Unit-1 has been successfully synchronized with National Grid with coal on 28.10.24. 

•    Chimney-1 is operational. In Chimney-2, flue-can erection completed and borosilicate lining is in progress. FGD & AHP works for Unit-1 nearing completion. 

•    Ash Dyke Lagoon-1, 2 & OFL is ready for charging.

•    400 kV Switchyard, Transmission Lines & Sub-station are ready for power evacuation.
•    CT-1 is ready. In CT-2 all fans, motors, gearbox installed. Cable laying also completed: Panel testing and instrumentation work nearing completed.

•    Wagon Tippler-1, Coal Crusher and Coal path-1 including SR-1 is also ready. Stacking and reclaiming of coal in stockyard has been commenced. WT-2 equipment erection in progress. 

•    Downline from Danwar station of Indian Railways to Khurja STPP is already operational. Railway siding works nearing completion.

•    In Unit-2, all GTs, UTs placed at foundation and associated erection works/ testing taken up. Further, main boiler, ESP, FGD and other associated works are in progress. 

•    Facility for water supply from Ganga canal at Mundakhera to Khurja STPP is operational long back and water is being supplied to the Khurja plant.