Generation & Billings

MONTHWISE GENERATION DETAILS FROM TEHRI DAM & HPP(STAGE-I) FOR FY 2018-2019
S.N Month Generation Target (MU) Monthly Generation Target (MU) Commulative Gross Generation (MU) Monthly Gross Generation (MU) Commulative Scheduled Generation (MU) Monthly Scheduled Generation (MU) Commulative Scheduled Energy Monthly SCHEDULED ENERGY COMMULATIVE Remark
1
April, 2018 195.04 195.04 157.42 157.42 156.50 156.5 70.71 70.71 As per Pro. REA dtd 04.05.2018 issued by NRPC for April, 2018
2
May, 2018 146.04 341.08 128.47 285.89 127.10 283.6 67.25 137.96 As per Pro. REA dtd. 07.06.2018 issued by NRPC for May, 2018
3
June, 2018 121.74 462.82 172.95 458.84 171.95 455.55 75.32 213.28 As per Pro. REA dtd. 05.07.2018 issued by NRPC for June, 2018
4
July, 2018 271.04 733.86 236.18 695.02 233.98 689.53 104.10 317.38 As per pro. REA dtd. 03.08.2018 issued byNRPC for July, 2018
5
August, 2018 690.79 1424.65 612.73 1307.75 603.90 1293.43 213.47 530.85 As per pro. REA dtd. 05.09.2018 issued by NRPC for August, 2018